Ethereum developers reach rough consensus to keep higher storage fees in Glamsterdam plan

Ethereum core developers reached rough consensus to proceed with Glamsterdam as proposed, CoinDesk reported on November 27, 2026. The upgrade plan retains a disputed increase in the cost of creating permanent on-chain data. If the change takes effect, some existing smart contracts could run out of gas mid-transaction, causing the transaction to fail.

Security firm ChainSecurity said it found 200 issues in applications including bridges, wallets and exchanges. Of those issues, 24 require teams either to upgrade the affected application or to migrate users and funds to a new one.

Affected teams must fix the most serious issues before the final public test on December 15, 2026. The deadline for the remaining fixes is January 10, 2027. CoinDesk cited earlier developer discussions that put mainnet activation in mid-January 2027 at the earliest, not on a confirmed date.